Woolworths Fairy Meadow

In collaboration with Woolworths and AGL, Canyon Solar installed this 167kWp system in a busy live carpark. The site had many complexities, including limited construction hours, site access constraints and stormwater coordination. However, Canyon Solar delivered the system in 5 weeks, from foundations to handover. This system was installed ready for EV charging, which was retrofitted in March 2025.

Location: Fairy Meadow, NSW
Completion Date: April 2024
Client: AGL
End Client: Woolworths